Question no 1324 : PP Strategy Group 10

In SAP PP Planning Strategy Group 10 ("Make to Stock Gross Planning"), at MRP run; which the following it will consider EXCEPT?

(only one answer)

A)    Stocks.
B)    Sales Order.
C)    Planned Independent Requirements.
D)    Existing Production Orders.
E)    Safety Stock.
.