In SAP PP, consider the following and identify the correct PP MRP Strategy ?
- Do not consider Stocks.
- Do not consider Sales Order.
- Allow Planned Independent Requirements.
(only one answer)
A) Strategy "10".
B) Strategy "11".
C) Strategy "20".
D) Strategy "30".
E) Strategy "40".
.
- Do not consider Stocks.
- Do not consider Sales Order.
- Allow Planned Independent Requirements.
(only one answer)
A) Strategy "10".
B) Strategy "11".
C) Strategy "20".
D) Strategy "30".
E) Strategy "40".
.
Answer: B