In SAP APO SNP, which of the following depict the correct sequence of SNP Planning Process ?
(only one answer)
I) Execute TLB Run.
II) PP/DS Run.
III) Execute Deployment Planning Run.
IV) Execute SNP Run.
V) Release Demand Plan.
VI) Check/Resolve SNP Run Issues.
A) I, III, II, IV, VI, V.
B) V, I, III, IV, V, II.
C) V, VI, IV, III, I, II.
D) V, VI, IV, II, III, I.
E) V, IV, VI, II, III, I.
Answer: E