In SAP APO SNP, Check the understand of SNP and PPDS Horizons for the TRUE depictions ?
(more the one answers)
A) It is not possible to have the PPDS Horizon comes after the SNP Horizon.
B) PPDS planning runs only takes place within the PPDS Horizon.
C) The PPDS and SNP Horizons are CIFted to APO from R/3’s planning time fences in the material master MRP 1 view.
D) Pegging requirements are not possible in SNP planning results.
E) SNP run is purely based on Quantity and Periods.
.
Answer: B, D, E