Which of the following true about Version Controls in SAP PP ?
(more then on answer)
A) There can be only one active version in SOP Planning for each material and plant combination.
B) There can be only one active version in Planned Independent Requirement for each material and plant combination.
C) There can be only one active capacity version for each work center and plant combination.
D) There can be only one active Planned Independent Requirement versions assigned to each Long Term Planning Scenario.
E) There can be only one active version of Planned Independent Requirement present on the Stock Requirement List for each material and plant combination.