Question no : 915 PP-MD material master collective indicator

In order to Switch the component and sub-assembly material behavior to make-to-stock even if it is assigned to a finished goods with a Make-to-Order Strategy, which of the following setting is appropriate ?

(only one answer)

A)    Assign the Individual/Collector indicator = "1" to the BOM header.
B)    Assign the Individual/Collector indicator = "2" to the BOM header.
C)    Assign the Individual/Collector indicator = "1" to the Component/Assembly in the MRP4 view.
D)    Assign the Individual/Collector indicator = "2" to the Component/Assembly in the MRP4 view.
E)    Assign the Individual/Collector indicator = "2" to the Component/Assembly in the MRP2 view.
.