Question no : 916 MM-MD Extend Material Master to new Plant

A material master has been created for a material in Plant 1000. You want to extend the material master to Plant 1100 for Purchasing, Storage and Accounting views. Which transaction would you recommend ?

A)    MM50 Extend data views.
B)    MM02 Change material master.
C)    MM01 Create material master.
D)    MM21 MRP Profile.
E)    MM60 Material list.
.