When transferring material master from R/3 to APO, materials with MRP type "X0" to be included in the integration model are said to be SCM-relevant master data, what is the significance of this material in the R/3 System ?
(more then one answer)
A) In R/3 SOP, MPS, MRP planning no longer recognizes this material.
B) In R/3 MPS, MRP planning no longer recognizes this material.
C) In R/3 the material is no longer seen in the Stocks Requirements list.
D) In R/3 the material can be allowed MRP planning run but not MPS planning run.
E) In R/3 the material need not have a Bills of Material and Routing.
,
Answer: B