TERP10 Unit 4 Material Planning
.
An MRP run cannot generate which of the following MRP elements ?
I) Purchase Requisition.
II) Purchase Order.
III) Production Order.
IV) Schedule Lines.
V) Contract.
(Select ONE best answer)
A) V only.
B) III, V.
C) III, IV, V.
D) II, III, V.
E) I, II, III, IV, V.
.
Answer: D