Question no : 478 PS Logistics Concepts

TERP10 (Unit 10) Program and Project Management 
.
An _____________ activity determines the output to be provided by machines or personnel in order to complete the activity. 
   
(Select ONE best answer)

A)   Cost activities.
B)   External services.
C)   Internal processing.
D)   External processing. 
E)    3rd party order.