Question no 2570 : Identify the planning process

In SAP ERP Production Planning and Manufacturing, a product group is created where sales plan is transferred from SIS, it is then disaggregated and transfer to demand management, which of the following process the above has been described ?

(only one answer)

A)   Sales and Operations Planning.
B)   Supply Network Planning.
C)   Master Production Scheduling.
D)   Capacity Requirement Planning.
E)   Material Requirement Planning.
.

Tuesday, September 14, 2010

Question no : 514 PP MRP mechanics

TERP10 Unit 4 Material Planning
Which of the following is data element determines a material for make-to-stock or make-to-order scenario ? 

A)   MRP type. 
B)   MRP strategy. 
C)   Procurement type. 
D)   Lot sizing key. 
E)    Individual/collective indicator. 

Question no : 513 PP MRP Mechanics

TERP10 Unit 4 Material Planning
Which of the following depict the correct mechanical steps of an MRP run ?

I)    Net requirement Calculation.
II)   Lot sizing Rule.
III)  BOM explosion.
IV)  Scheduling.
V)   Procurement type. 

A)   III, II, I, IV, V. 
B)   I, II, V, IV, III. 
C)   I, II, III, IV, V. 
D)   III, I, II, IV, V. 