TERP10 Unit 6 Manufacturing Execution
.
When can you perform the goods receipt for a production order ?
I) After the production order is released.
II) After goods issue has been carried out.
III) After confirmation has been carried out.
IV) When the production order is ready for technical completion.
V) When availability check is completed.
(Select ONE best answer)
A) I only.
B) I, II.
C) I, II, III, IV.
D) I, II, III.
E) I, II, III, IV, V.
.
Answer: A
ReplyDelete