TERP10 Unit 4 Material Planning
.
Which of the following depict the correct mechanical steps of an MRP run ?
I) Net requirement Calculation.
II) Lot sizing Rule.
III) BOM explosion.
IV) Scheduling.
V) Procurement type.
I) Net requirement Calculation.
II) Lot sizing Rule.
III) BOM explosion.
IV) Scheduling.
V) Procurement type.
A) III, II, I, IV, V.
B) I, II, V, IV, III.
C) I, II, III, IV, V.
D) III, I, II, IV, V.
E) I, II, IV, III, V.
.
Answer: B
ReplyDelete