TERP10 Unit 3 Procurement Cycle
.
The vendor makes material available, which you then manage it in quantities. A liability only arises when material is withdrawn into own stocks or issued for consumption. What scenario was described above ?
(Select ONE best answer)
A) Subcontracting.
B) Blanket order.
C) Third party.
D) Consignment.
E) Returnable transport packaging.
.
Answer: D