Question no : 504 PP Execution Confirmation



TERP10 Unit 6 Manufacturing Execution 
Which of the following confirmation technique is best used for continuous counting of production results for an hourly confirmation entry ? 
  
(Select ONE best answer)

A)   Time ticket confirmation.
B)   Progress confirmation.  
C)   Time event confirmation. 
D)   Collective entry. 
E)    Milestone confirmation.    