TERP10 Quiz Unit 04 Material Planning
The _______________ controls how a material is to be procured (for example in-house production or external procurement).
A) Material type.
B) MRP type.
C) Lot sizing procedure.
D) Procurement type.
E) Production procedure.
.
Answer: D