Question no : 420 PP Master Data Capacity Calculation

TERP10 Quiz Unit 06 Manufacturing Execution

Calculate the availability capacity based on the following work center capacity data ?   
    start time is 09:00
    finish time is 19:00
    break time is 2 hours
    number of capacity is 5 units
    efficiency 90%

A)     45 hours.
B)     36 hours.
C)     40 hours.
D)     48 hours.
E)     54 hours.
. 