TERP10 Quiz Unit 06 Manufacturing Execution
Calculate the availability capacity based on the following work center capacity data ?
start time is 09:00
finish time is 19:00
break time is 2 hours
number of capacity is 5 units
efficiency 90%
finish time is 19:00
break time is 2 hours
number of capacity is 5 units
efficiency 90%
A) 45 hours.
B) 36 hours.
C) 40 hours.
D) 48 hours.
E) 54 hours.
.
Answer: B