TERP10 Quiz Unit 04 Material Planning
The results of an MRP run can create the which of the following MRP elements:
I) Planned Orders.
II) Purchase Requisitions.
III) Purchase Order.
IV) Production Order.
V) Schedule Lines.
A) I, II only
B) I, II, IV, V.
C) I, II, III, IV, V.
D) I, II, V.
E) I only.
.
Answer: D