TERP10 Quiz Unit 04 Material Planning
Which of the following are TRUE about SOP and Planned Independent Requirements ?
I) There can be only one active version in SOP.
II) There can be only one active version in Planned Independent Requirements.
III) There can be more then one active version in SOP.
IV) You can disaggregate and transfer only an active version of the SOP to the Independent Requirement.
V) The contents of a product group can be either another product group or material.
A) I, II, IV
B) II, III, IV
C) I, II, IV, V
D) I, IV, V
E) I, V
.
Answer: E