This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Saturday, August 28, 2010

Question no : 428 PP Execution Goods Receipt

TERP10 Quiz Unit 06 Manufacturing Execution
.
Which of the following is TRUE about goods receipt to a production order ? 
.
I)      The production order is completed with a "TECO" status.
II)     The production order is credited.
III)    A material document is created.
IV)    The material master accounting view is updated.
V)     Overhead costs is calculated to debited to the production order.
.
A)     I, III, IV.
B)     I, III, IV, V.
C)     II, III, IV.
D)     II, III, IV, V.
E)     I, II, III, IV, V.
. 