In SAP PP, a goods issue to the Production Order:
I) Reduces the reservations quantities of the material.
II) Sets a system status to the material component in the Production Order.
III) Debits additional costs to the Production Order.
IV) Always initiate an MRP run for replenishment of the issued quantity.
A) I, III
B) II, IV
C) I, IV
D) I, II
E) I, II, III
.
Answer: A