Question no 1645: Maintenance Plan for External Services

In SAP PM ECC6.0, which of the following statements are true about the use of Maintenance Plan for External Services ?

(only one answers)

A)    Only one service master can be entered in the Maintenance Plan.
B)    One or more framework PO can be entered in the Maintenance Plan.
C)    Only one technical object can be entered in the Maintenance Plan.
D)    One or more technical objects can be entered in the Maintenance Plan.
E)    No technical object can be entered in the Maintenance Plan.
.

2 comments:

  1. Using IP40 for Maintenancwe Plan using Service Procurement, you can only enter the following:
    . One Maintenance Item only for each Maintenance Plan

    With the Maintenance Item, only the following can be entered:
    . One Framework PO with validity period
    . One G/L Account for the Expense Account at Service Entry Sheet Approval
    . One Settlement Order
    . One or more Service Spcifications (Service Masters)

    However, IP40 as at ECC6.0 does not allow entry of Technical Objects.