Question no 1640: Sychronization of Equipment and Serial

In SAP PM as of ECC6.0, the setting in-order to synchronize the equipment and serial number is done where ?

(only one answer)

A)   Material type configuration.
B)   Serial profile configuration.
C)   Serial level in the Plant/Storage view.
D)   Equipment type.
E)   Serial number range.
.