In SAP PP ECC6.0, a company wish to plan the MRP run based on the total of Sales orders and Planned Independent requirements as each are for different customers, which of the following strategy do you think is appropriate ?

(only one answers)

A)   Strategy 10.
B)   Strategy 20.
C)   Strategy 30.
D)   Strategy 40.
E)   Strategy 50.
.

2 comments:

  1. Strategy 30 considers the Sales Order and Planned Independent Requirements Separately; in this Strategy, the Sales Order does not consume or reduce the Planned Independent Requirements. The Strategy is classified as a Make to Stock Strategy.