In SAP PM ECC6.0, The Service Profile and Response Profile assigned to the Notification type will allow you to do which of the following ?
(more then one answers)
A) Default the Task codes into the Task folder in the Notification.
B) Default the Activities codes into the Activities folder in the Notification.
C) Calculate the Task codes Planned finish date and time.
D) Calculate the Activities codes Planned finish date and time.
E) Define the service window available for the Planned finish date and time calculation.
.
(more then one answers)
A) Default the Task codes into the Task folder in the Notification.
B) Default the Activities codes into the Activities folder in the Notification.
C) Calculate the Task codes Planned finish date and time.
D) Calculate the Activities codes Planned finish date and time.
E) Define the service window available for the Planned finish date and time calculation.
.
Answer: A, C, E
ReplyDeleteB, D) Activity codes in the Activities folder are for immediate actions taken and not relevant for the Service profile scenario.
ReplyDelete