This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, July 13, 2012

Question no 1613: Call Horizon

In SAP PM ECC6.0, When the Call Horizon is 0 %, ___________________ .

(only one answer)

A) The Planning will be done for the entire horizon of the scheduling period.
B) The Call Date is exactly one cycle before the Plan Date / Due Date.
C) The Call Date is exactly one cycle later then the Plan Date / Due Date.
D) The Call Date = Plan Date / Due Date.
E) This is not possible as 0 (Zero) is not a valid entry.
.

2 comments:

  1. It is indeed one cycle before the plan date, and if the call horizon is 100%; the plan date is equal to the call date.

    ReplyDelete