In SAP PM ECC6.0, When the Call Horizon is 100 %, ___________________ .
(only one answer)
A) The Planning will be done for the entire horizon of the scheduling period.
B) The Call Date is exactly one cycle before the Plan Date / Due Date.
C) The Call Date is exactly one cycle later then the Plan Date / Due Date.
D) The Call Date = Plan Date / Due Date.
E) The Call Date is at the end of the horizon of the scheduling period.
.
Answer: D
ReplyDeleteIf the call horizon is 100%; the plan date is equal to the call date. And if the call horizon is 0%, then the call date is exactly one cycle before the plan date.