Question no 1614: Hiearchy in Maintenance Packages in Preventive Maintenance

In SAP PM ECC6.0, which of the following are true about Hiearchy in Maintenance Packages in Preventive Maintenance ?

(more then one answers)

A) If two packages with the same hierarchy are due at the same time, then both packages are performed.
B) If two packages have different hierarchies, only the package with the higher hierarchy is performed.
C) If two packages with the same hierarchy are due at the same time, then the package with the least operation time is performed.
D) If two packages have different hierarchies, only the package with the higher operation time is performed.
E) If two packages with the same hierarchy are due at the same time, no packages will are performed.
.