Partial confirmation with the status “PCNF” status in Time Confirmation option allows which of the following process ?
(more than one answers)

(A) Partial Confirmation done can be partially reversed.
(B) Partial Confirmation done must be reversed in full.
(C) Full Confirmation “CNF” can be done in the following confirmation step.
(D) Additional costs can be posted but the account assignment data is fixed.
(E) Account assignment data is changeable but additional costs cannot be posted.
.