Question no : 551 PM Organization Structure Configuration

PLM300 Plant Maintenance
Unit 02 Plant Maintenance Organization

Project IMG views are created for ……….
(only one answer)

(A) A checklist for the Customizing activities that should be configured for each Project IMG to process project documentation, project-wide documentation, and relevant information on project information.

(B) Necessary as the project IMG itself do not allow configuration and documentation, there is a minimum of one project IMG view for each Project IMG to process project documentation, project-wide documentation, and relevant information on project information.

(C) Link to ASAP directly for the project IMGs to process project documentation, project-wide documentation, and relevant information on project information.

(D) Better interface screens for the project IMGs to process project documentation, project-wide documentation, and relevant information on project information.

(E) Better structuring for the project IMGs to process project documentation, project-wide documentation, and relevant information on project information.
.