PLM300 Plant Maintenance
Unit 05 Corrective Maintenance
When a non-stock material is created in the maintenance order, which of the statements do not correctly depict its functionality :
(more than one answers)
(A) A purchase requisition is always automatically generated.
(B) A purchase order can be created manually in the maintenance order.
(C) Goods receipt can only be entered with reference to the purchase order after the order has been put in process.
(D) Goods receipt can be entered with reference to the purchase order before or after the order has been put in process.
(E) Invoice verification of the purchase order will never affect the costs of the original purchase order value posted as it is integrated from materials management to accounts payable.
.
Answer: B, D, E