In SAP PM, when will the system update the Maintenance Operation of Control Key "PM03" (External Services Procurement) to system status of "EOPD" ?
(only one answer)
A) When the External Services Purchase Requisition is created.
B) When the External Services Purchase Order is created.
C) When the External Services Operations in the Maintenance Order is Released.
D) When the External Services Purchase Order's Service Entry Sheet is entered.
E) When the External Services Purchase Order's Service Entry Sheet is approved.
.
(only one answer)
A) When the External Services Purchase Requisition is created.
B) When the External Services Purchase Order is created.
C) When the External Services Operations in the Maintenance Order is Released.
D) When the External Services Purchase Order's Service Entry Sheet is entered.
E) When the External Services Purchase Order's Service Entry Sheet is approved.
.
System status "EOPD" (External Services Partially Delivered) or "EODL" (External Services Delivered) are set to the operation when the Service Entry Sheet is approved.