In SAP PM, which of the following scenarios results in Purchase Requisition generated in the Maintenance Order ?
(more then one answers)
A) Item Category "R" for components.
B) Item Category "N" for components.
C) Control Key "PM02" for operations.
D) Control Key "PM03" for operations.
E) Control Key "PM05" for operations.
.
(more then one answers)
A) Item Category "R" for components.
B) Item Category "N" for components.
C) Control Key "PM02" for operations.
D) Control Key "PM03" for operations.
E) Control Key "PM05" for operations.
.
Answer: B, C, D
ReplyDeleteBasically item category "R" is variable size item and it has similar characteristics in terms of procurement and inventory processes of item category "L" while PM05 is for internal confirmation (external contractor). Both do not have purchase requisition from the maintenance order.
ReplyDelete