In SAP MM, in order to use JIT and Forecast Scheduling in the Scheduling Agreement, you must have which fo the following setup ?
(more then one answers)
A) Assign the Creation Profile in the Purchasing Organization data level of the Vendor Master.
B) Assign the Creation Profile in the Purchasing Organization's Plant subrange data level of the Vendor Master.
C) Assign the JIT requirement indicator in the Material Master Purchasing view.
D) Assign the Forecast requirement indicator in the Material Master Purchasing view.
E) Set the "Release documentation" indicator in the relevant Scheduling agreement document type.
.
B) The data field "creation profile" which is primarily used to detremine the JIT or Forecast schedule from the Delivery Schedule, the data field can be foun at the Plant Subrange of the Vendor Master Purchasing Data View.
ReplyDeleteC) The JIT schedule is optional, if it is required then you can set in at the Material Master Purchasing view at the Plant level.
ReplyDelete