In SAP MM up to ECC6.0 Extension set 2, which of the following is TRUE about Release Strategy in MM Purchasing Document usage ?

(more then one answers)

A)    Item-level Release Strategy is only relevant for Purchase Requisition.
B)    The class type for Release strategy for all Purchasing document types is the same.
C)    Each Purchasing document type has its own communication table for reference characteristics creation.
D)    Maximum Release codes in a Release Strategy for Purchase Requisition is 8.
E)    The field selection key is assign to the Release Indicators.
.

1 comment:

  1. Only the PR document type can be set for release strategy at the header level (overall release) or at the item level. Other Purchasing document's release strategy are all at Item level. (as at ECC6.0)

    The Class type is 032 for release strategy for all Purchasing Document types.

    The Communication table for PR is "CEBAN" while other Purchasing Documents are "CEKKO".

    You can find maximum of 8 Release codes in a Release Strategy for PR.

    Release indicators can be assigned with a field selection key so that after a certain stage of approval, creation data contents are no longer changeable.