In SAP MM, which of the following processes are not possible for transaction code ME59N ?
(more the one answers)
A) Assign vendor.
B) Flag for RFQ.
C) Convert PR to RFQ.
D) Convert PR with Contract to Contract Release Order.
E) Convert PR with Scheduling Agreement to Delivery Schedule.
.
Answer: A, B, C
ReplyDeleteME59N expects the Purchase Requisition with Vendor Assigned, and with both Material Master and Vendor Master flagged with the "Auto PO" indicator before it can automatically converts them to Purchase Orders.
ReplyDeleteNo RFQ processing is possible in ME59N.