This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, March 19, 2010

Question no : 326 PP SOP Concepts


TERP10 (Unit 4) Material Planning 

When Sales Operation Plan's (SOP Plan) are completed, it is disaggregated and transfer to the next level of planning as ___________________ .

(Select ONE best answer)

A)   Planned Independent Requirement.
B)   Master Production Schedule. 
C)   Production Schedule. 
D)   Execution Plan.
E)    MRP elements. 