SAP What is # 8 - What is Backward Overlap ?

SAP What is # 7 dealt with Forward Overlap concept, this one is on Backward Overlap.

Assuming Lot size "ZB" with with '-' for Backward overlap as below.


From SAP的学习和考试 Learning & Examination

And the material master is fine tuned with the following as below:
1) max lot size of 100
2) takt time of 1


From SAP的学习和考试 Learning & Examination
 
The results of
MRP run on a Planned Independent Requirement of 550 as below:
1) The maximum lot size of 100 only allow planned order of max size 100.
2) Takt time 1 backward each planned order from the requirement date.


From SAP的学习和考试 Learning & Examination


Here is the factory calender:
And the factory calender is adhered to.


From SAP的学习和考试 Learning & Examination
 
CONCLUSION: Similar to the Forward Overlap parameter, the Backward Overlap parameter is just the opposite.

APPLICATION: In this case, coupled with the maximum lot size parameter, the backward overlap impose a strict delivery quantity requirement based on the cycle time / takt times. At the same time respecting the factory calender. This is useful to staggered the delivery for production consumption due to space in the warehouse.

CAUTION: Consider the use of combining these fine-tuning parameters by creating a new lot-size key. Test them thoroughly before use.
.