TERP10 (Unit 6) Manufacturing Execution
_________ is a lot-size independent time element and ___________ is a lot-size dependent time element within the definition of an operation in a Routing.
(Select ONE best answer)
A) Independent time, Dependent time.
B) Setup time, Variable time.
C) Fixed time, Machine/Labour time.
D) Fixed time, Variable time.
E) Setup time, Machine/Labour time.
.
Answer: E