Question no 4062 : Serial Level for Equipment-Serial link

In SAP Plant Maintenance as at S/4 1909, when the Serial Master linked to the Equipment was found to not have the same numbers (ie Serial and Equipment not having the same number), which of the following could be true ? 

(only one answer)

A) The Serial Level assigned to the Serial Profile in the Configuration was set with "Serialization with the Stock Material Number". 
B) The Serial Level assigned to the Equipment Category in the Configuration was set with "Serialization with the Stock Material Number". 
C) The Serial Level assigned to the Plant in the Configuration was set with "Serialization with the Stock Material Number". 
D) The Serial Level assigned to the Material Master was set with "Serialization with the Stock Material Number". 
E) The Serial Level assigned to the MIGO (Goods Movement) item detail screen was set with "Serialization with the Stock Material Number". 
.

Answer: D

Serial Level and Serial Profile is the Plant/Storage 2 view in the Material Master