In SAP QM as at ECC6.0 EhP6, which of the following are the per-requisites for Incoming Certificate requirements ?

(more than one answers)

A)  QM control key with indicator Certificate required is set.
B)  A certificate type has been defined and the indicator for enhanced certificate processing is set.
C)  A number range for the certificate receipt is defined.
D)  QM procurement active in the Material Master QM data view.
E)  The Inspection Type assigned to the Material Master must be activated for Incoming Certificate.