In SAP QM ECC6.0 EhP6, to ensure a Sampling Procedure is a required entry when it is assigned to an operation in the Inspection Plan, what should you do ?
(only one answer)
A) Set 'Sampling Procedure' requirement indicator in the Master Inspection Characteristics.
B) Set 'Sampling Procedure' requirement indicator in the Inspection Type activation screen in the Material Master QM data view.
C) Parameter ID on the Sampling Procedure to the User.
D) Set 'Sampling Procedure' field selection for transaction code IP01.
E) Set 'Sampling Procedure' requirement indicator in the Inspection Plan Header.
.
(only one answer)
A) Set 'Sampling Procedure' requirement indicator in the Master Inspection Characteristics.
B) Set 'Sampling Procedure' requirement indicator in the Inspection Type activation screen in the Material Master QM data view.
C) Parameter ID on the Sampling Procedure to the User.
D) Set 'Sampling Procedure' field selection for transaction code IP01.
E) Set 'Sampling Procedure' requirement indicator in the Inspection Plan Header.
.
Answer: A
ReplyDeleteSet the requirement indicator for Sampling Procedure entry in the Master Inspection Characteristics.