Question no 2706 : Calibration recording integration

In SAP QM as at ECC6.0 EhP6, the results recording on the Inspection Characteristics can be written as Measuring Documents of the Measuring Points in the Equipment is possible when ________________________ . (also relevant for PM Certification knowledge)

(only one answer)

A)   The Master Inspection Characteristics is linked to the Characteristics used to create the Measuring Point in the Equipment Master.
B)   The Master Inspection Characteristics is linked to the Equipment Master classification characteristics.
C)   The Equipment category in the customizing was set with an indicator that activates the PM-QM integration for data transfer from QM to PM.
D)   The User profile has been assigned a transfer data option from QM to PM.
E)   The Master Inspection Characteristics was set with a 'transfer' indicator.
.

1 comment: