In SAP MM, which of the following purchasing document need not necessary be created without a Plant ?

(more the one answers)

A)     Purchase Requisition.
B)     RFQ.
C)     Purchase Order.
D)     Contract.
E)     Scheduling Agreement.
.

2 comments:

  1. You can create the RFQ without a Plant, the purpose is to negotiate a price from the vendor for all plants. When the Quotation is approved, an info record without plant can be generated.

    ReplyDelete
  2. A Central contract can be created without a Plant. However, SAP's scheduling agreement is design to be plant specific.