In SAP MM, in-order for the to setup a Purchase Order cannot be received after a certain number of days after the delivery date, which of the following settings are required ?

(more then one answers)

A)    The desired outcome of "Warning" or "Error" must be set to the "last possible delivery date" Message number.
B)     The plant must be configured to allow this checking.
C)     The number of working days from the delivery date is to be assigned to the Plant in the configuration.
D)     The "Latest delivery date" to be entered in the Purchase Order item.
E)     The plant and the movement type for the goods receipt must be configured to allow this checking.
.