In SAP MM and PP, which of the following are true about MRP ?
(more the one answers)
A) A material master is necessary for MRP planning.
B) A material master without the Accounting view is not valid for MRP planning.
C) A material master without the Plant/Storage view is allowed for MRP planning.
D) A material master MRP1 view without the MRP group is not optimized for MRP planning.
E) A material master need not have an Accounting view for MRP planning.
.
(more the one answers)
A) A material master is necessary for MRP planning.
B) A material master without the Accounting view is not valid for MRP planning.
C) A material master without the Plant/Storage view is allowed for MRP planning.
D) A material master MRP1 view without the MRP group is not optimized for MRP planning.
E) A material master need not have an Accounting view for MRP planning.
.
Answer: A, C, E