In SAP MM & PP, the "Planned Delivery time" __________________________ .
(more then one answers)
A) Can be found in the MRP 2 view of the Material Master.
B) Is a mandatory field for Externally procured material.
C) A vendor master is necessary to be entered together with it in the MRP 2 view of the Material Master.
D) Can be found in the Vendor master Purchasing data view.
E) Is available in the Purchasing Info Record.
.
Answer: A, B, E