In SAP Production Planning & Distribution, Pull List (MF60) will be able to perform staging for which of the following MRP elements ?
(more than one answers)
A. Repetitive Planned Orders.
B. Planned Production Orders.
C. Production Orders.
D. Process Orders.
E. Stock Transfer Requirements.
.
Answer: A, B, C, D