In SAP PP, a production environment using SAP wish to create 3 common packing lines as separate work centers but wish to maintain only one capacity category as the packing labors are shared among the 3 packing lines; what would you suggest ?
(select the best single answer)
A) Capacity Hierarchy.
B) Capacity Category.
C) Pool Capacity.
D) Grouped Capacity.
E) Capacity Version.
.
(select the best single answer)
A) Capacity Hierarchy.
B) Capacity Category.
C) Pool Capacity.
D) Grouped Capacity.
E) Capacity Version.
.
Answer: C
ReplyDeletePool capacity allows you to split to several work centers but maintain one capacity category for capacity evaluation.
ReplyDelete