Question no 1113 : Lot Size calculation

In SAP MM PP, Please use the following information to derive the expected MRP calculation results of the Lot Size ?

Current Stocks = 200
Safety stock = 200
No other MRP element
MRP type is Re-Order Point "VB" with ROP at 200
Lot Sizing key is "EX"

(only one answer)

A)    A Planned Orders of 200.
B)    A Planned Orders of 400.
C)    A Planned Orders of 800.
D)    No Planned Orders are calculated.
E)    A Planned Order of 600.
.